Tuesday, May 23, 2017

ASK THE BORED: A progress report on paving, two-way streets and the crosswalk on Main at W. 1st.


From the BOW meeting of May 16, in their own words, an update on downtown grid paving and the crosswalk project at Main and W. 1st.

---

A MEETING OF THE BOARD OF PUBLIC WORKS & SAFETY OF THE CIVIL CITY OF NEW ALBANY, INDIANA, WAS HELD IN THE THIRD FLOOR ASSEMBLY ROOM AT THE CITY/COUNTY BUILDING ON TUESDAY, MAY 16, 2017 AT 10:00 A.M.

PRESENT: Mickey Thompson, member, Cheryl Cotner-Bailey, member, and Warren V. Nash, president. 

OTHERS PRESENT: Fire Chief Juliot, Fire Marshal Koehler, Mike Hall, Sandy Boofter, Chris Gardner, Bryan Slade, Sidney Main, Larry Summers, David Hall, Jessica Campbell, Police Chief Bailey, Alicia Meredith, Courtney Lewis and Mindy Milburn

(excerpt follows)

Sunny Dickerson, HWC Engineering, reported on the progress of the two-way conversion. He explained that the underground conduit is in on Spring Street as well as the pit bores for the detector houses. He stated that they are starting on Elm Street today and they should be done with that by the end of the week. He added that the work will be contingent upon MAC completing their paving work but as of right now everything looks to be on schedule.

Wes Christmas explained that the south side of the milling is completed and they are already working on the north side, so it should be completed today. He stated that there may be a few side streets that need to be finished but they plan to start paving tomorrow. He explained that the plan is to have all the paving work completed by Thursday and Friday if the weather cooperates. He stated next week is an off week for paving activities while they wrap up the underground work, and the week of May 30th they will begin the same process on Elm Street.

Mr. Nash asked about the temporary markings that will be put out.

Mr. Christmas explained that it will be the same configuration as it is now and will not change until all the new signage and signals are complete.

Mr. Nash asked if Market would be done after Elm

Mr. Christmas replied yes and explained that all paving is anticipated to be complete before the end of June. He added that Police Chief Bailey suggested installing additional signage to let the residents and businesses know what is going on so they have small signs every 30 feet down the corridor as well as an additional message board.    

Mrs. Cotner-Bailey asked if they could have door hangers.

Mr. Christmas explained that they haven’t done it in the past but they could check on that if they need to.

Mr. Nash asked if the signs have been working.

Police Chief Bailey stated that there hasn’t been a tremendous problem and they have the few incidents under control. 

Mr. Summers asked Mr. Christmas to touch on the West 1st and Main Street project.

Mr. Christmas explained that this is for the bump-outs and pedestrian crossings and the work is under way. He stated that the majority of the concrete is poured on the southeast corner and they started demo on the southwest corner. He explained that once the south side is done they will jump over the north side and do the other two corners. He added that beyond the intersection the only work that is being done is the addition of a few trees.

Mr. Nash commented that some of the trees on State Street look too big for the bump-outs.

Mr. Christmas stated that the trees were suggested by Greg Mills and are supposed to be of a smaller variety. 

No comments:

Post a Comment